Bumi Armada’s Transport and Installation experience is summarised below:

A) SEPAT FIELD, OFFSHORE TERENGGANU
Client: Petronas / Petrofac

  • Completed the installation of two 6" risers from the FSO Sepat to the mobile offshore production unit at the Sepat field, offshore Terengganu.
  • Completed the mooring pre-setting and the hook up for the FSO.


B) FILANOVSKY FIELD,CASPIAN SEA
Client : LukOil

EPIC contract was awarded back in April 2012 for the installation and burial of approx. 90km of subsea pipelines
based on different diameters between Filanovsky and Korcaghin fields. The project scope includes:
  • Procurement of line pipes, anodes, flanges and associated fittings and permanent items
  • Installation of subsea pipelines ranging between 4.5" and 22"
  • Dredging excavation works
  • Post-trenching and mechanical backfilling of all installed pipelines
  • Installation of subsea tie-in spools
  • Pre/post lay survey
  • Pre-commissioning of installed pipeline and tie-ins
Installation is due to commence mid-2013.

C) CASPIAN SEA, OFFSHORE TURKMENISTAN
Client: Momentum Engineering (LLC) Turkmenistan Branch No. 14841294.
Final Client: Dragon Oil

  • We have been involved in installation of approx. 15km of submarine pipelines of difference sizes between the various Blocks of LAM field located offshore Turkmenistan.


D) TE GIAC TRANG, VIET NAM
Client: HLJOC, 43m water depth

  • Preset of the FPSO 12 point mooring system (anchor piles, ground chain, excursion limiter chains and top chains),
  • Mid water arch jacket installation (1000Te structures in two parts, with the base piled and the jacket and gutter structure installed over the base with grouting operation)
  • Riser bottom guide frame (30Te skirted subsea structure),
  • FPSO tow from Keppel shipyard to location – Vietnam
  • FPSO hook up
  • Flexible risers system (7 off flexible risers) installation including tie-ins to the PLEM (scheduled in 2011)
  • Leak testing of the flexible risers from the FPSO
  • Installation of the dynamic umbilical from FPSO to PLEM
  • Installation of the export hose


E) OYO FIELD, NIGERIA
Client: ENI - Nigeria Agip Exploration Limited (NAE), (Perdana FPSO),
380m water depth.

  • Preset of the mooring (12 point spread mooring - 3 lines x 4 clusters, Stevpris anchors, ground chains, spiral strand wires and top chains)
  • FPSO transit from Keppel shipyard to location – Nigeria
  • FPSO hook up to its mooring
  • The mooring preset was done using the Normand Installer.


F) OKORO SETU FIELD, NIGERIA
Client: Afren (Armada Perkasa FPSO)

  • FPSO transit from Keppel shipyard to location (Nigeria)
  • Preset of the mooring (10 point spread mooring)
  • FPSO hook up to its mooring
  • Flexible riser system installation
  • Installation of the export hose